Modification 19 to the Kings Forest Stage 1 approval is currently on public exhibition through the NSW Planning Portal, with submissions closing on Friday, September 25.
According to the Department of Planning, the application seeks to increase the defined area available for earthworks, remove the existing limitation on exposed areas and replace it with performance criteria based on monitoring data.
The proposed changes relate to the large-scale earthworks needed to prepare sections of the site for development.
Existing approval conditions include measures intended to minimise erosion, dust and sediment impacts during construction, with earthworks currently subject to staged controls and environmental management requirements.