Delays and cost blowouts mean Victoria’s suburban rail loop is unlikely to be delivered within budget and on time, says the state’s spending watchdog.
The finding – from the Victorian Auditor-General’s Office – comes as the government reviews spending on the multibillion-dollar project.
“The Suburban Rail Loop Authority has made significant progress planning SRL East precincts and delivering early rail infrastructure works and is forecasting that it will deliver the project in line with the government’s announced cost and completion date targets,” said VAGO. “However, delays, cost increases and emerging risks mean this is not reasonably assured at this early stage.”
The Suburban Rail Loop is a 90-km corridor planned to link Melbourne’s eastern and western suburbs via Melbourne Airport. At a projected cost of $34.5 billion, it is Victoria’s largest infrastructure investment. VAGO concludes that the project “is more likely than not” to exceed its price tag.