Asante Gold (TSXV: ASE) announced on Monday that the construction and commissioning of the sulphide plant at its Bibiani gold mine in Ghana have been completed.

Asante has been ramping up activity at Bibiani throughout the year, funded by the initial $100 million deposit from Fujairah Holdings, its second-largest shareholder. The funding is part of a $500 million gold forward sale deal signed in December 2024.

In a press release, the company said the 12-hour-per-day operations to process Bibiani ore started on Saturday and will ramp up to 24 hours a day on Sept. 30. Optimization to achieve over 85% gold recovery will progress through October, taking the recovery rate from 60% to as high as 92% by month end, it added.

The project’s nameplate capacity is estimated at 4 million tonnes per year. Aerial drone footage of the plant can be viewed here.