The ECI phase, which began in February 2025, includes pre-construction surveying and design activities, bringing the project to a 30 per cent design level as it prepares for a financial investment decision expected in late 2025.
If approved, construction of the wind farm will begin in early 2026.
Located approximately 7km east of Georgetown in South Australia’s Mid North region, the wind farm is set to feature 42 wind turbines, a 118MW battery energy storage system, and a 12.8km 275 kV transmission line connecting to the Davenport to Brinkworth transmission line.
The project also plans for an access track network, underground medium-voltage cabling, and dedicated operations and maintenance facilities.
Carmody’s Hill Wind Farm is currently in advanced development, seeking a financial investment decision in late 2025 and aiming to commence construction in early 2026.